127 Sets Processing 4000mm 127 Sets High-Precision CNC Lathes
15 Years of Experience

CNC Knowledge: Design and optimization of the hinge bracket die casting process

The current development direction of the manufacturing industry is low pollution, light weight and high performance, and traditional manufacturing processes cannot meet the developments of the times. As the representative of high-precision manufacturing technology in special castings, die casting has the advantages of high dimensional accuracy, small machining allowance and high strength of parts. Among […]

cnc knowledge: design and optimization of the hinge bracket die

The current development direction of the manufacturing industry is low pollution, light weight and high performance, and traditional manufacturing processes cannot meet the developments of the times. As the representative of high-precision manufacturing technology in special castings, die casting has the advantages of high dimensional accuracy, small machining allowance and high strength of parts. Among the same type of die casting materials, die casting aluminum alloy has better thermoplasticity, lower linear shrinkage, good high temperature thermal resistance and physical and chemical properties, and is the first choice for die casting process materials. The mature die casting process has the characteristics of efficient production and high yield. However, the process cycle of new castings is long and relies on the experience of designers and actual production feedback. Repeated mold testing due to process optimization iterations leads to increased process costs and an extension of the production cycle, which significantly limits development. in the field of die casting. Therefore, CAE simulation is introduced into the field of die casting. By simulating the process of filling and solidifying molten metal, the structure of the casting system is analyzed and optimized to shorten the design cycle.

The hinge bracket studied in this paper has a complex structure and is a non-machining part. It meets strict requirements for dimensional accuracy and subsequent machining area. It is therefore produced using a die casting process. By analyzing the precision requirements of the structure and surface of the hinge bracket, two die casting processes were designed, and Anycasting software was used for numerical simulation. Both schemes were analyzed to predict possible defects such as pores, shrinkage porosity, shrinkage cavities and. cold insulation, location and reasons, select a better solution for process improvement and optimization, and finally perform production verification to provide a reference for the production of such parts.


1 Overall analysis of the parts

The hinge bracket is shown in Figure 1. The material is YL113 aluminum alloy. The chemical composition of YL113 aluminum alloy is shown in Table 1. The average wall thickness of the casting is 2.32mm, the maximum wall thickness is 5.63mm, the dimensions overall are 116mm × 82mm × 43mm and the weight is 131.64g. As shown in Figure 1, the casting structure is complex. The sleeve area and the multi-hole plate area are connected by arc surfaces and oblique straight surfaces. The cross section is half-I shaped and has an internal button shape. A large number of thin-walled transverse ribs are arranged on the outer wall, which requires molding without processing, the dark areas are polished and deburred, the shrinkage rate is 0.5%, and there are no defects molding such as shrinkage cavities and shrinkage. porosity.

Figure 1 Hinge bracket structure

1726822544228262.png

Table 1 Chemical composition of aluminum alloy YL113 wB/%


2 Die casting process design

2.1 Calculation of joint planes

The molded part is a part without machining. Thin-walled ribs with a draft angle of 5° are arranged on the outer wall. The cross section is shaped like a half-I shaped inner button. should be installed in the arc area, sleeve connection area and plate passage. A core pulling slider is arranged in the hole area, and an oblique pin side core pulling mechanism with a corresponding wedge angle of 20° is installed. According to the half-I-shaped cross-section structure of the hinge bracket casting and the principle of selecting the parting surface of the area with the largest projected area of ​​the casting, two parting surfaces were selected (Figure 2). In plane 1, the molded part is partially molded, and the position of the core draw core in the mold core (movable mold insert and fixed mold insert) is evenly distributed, which makes it easier to install and fix the mold. core. In option 2, the separation is carried out on the casting part, the size of the casting part can be guaranteed, and the parting surface is arranged on the grinding surface, so that the generated burr defects can be easily eliminated.

1726822579728256.png

Figure 2 Schematic diagram of the separation surface plan

2.2 Design of the portal system

Two casting systems were designed and the three-dimensional structural diagram is shown in Figure 3.

1726822595900203.png

Figure 3 Structural diagram of the casting system

2.2.1 Design of the interior slide

In scheme 1 of figure 3, in order to avoid direct contact between the channel and the core, the inner channel is arranged on the inner wall in order to shorten the casting process, the inner channel is arranged on the corresponding inner wall at the intersection of ; the ribs, and the casting liquid is filled along the ribs. The filling time is significantly shortened since the distance between the molten metal flowing to all parts of the cavity is as equal as possible, one large and two small inlet distribution patterns are formed. adopted. In the second option in Figure 3, in order to avoid the molten metal directly impacting the core, the casting method is changed to oblique casting, and since the stroke of the molten metal flowing towards the cavity is equal, a separate channel is arranged. The cross section of the portal is calculated as follows.

Image WeChat_20240920165406.png

In the formula: Ag is the cross section of the door, mm㎡; V is the volume of the pouring and overflow tank, mm³ the calculated cross section of the door Ag=138 m㎡;

2.2.2 Runner design

The structural shape of the side runner depends on the shape of the inside runner and the position of the core. The side of this casting is basically an inner loop area, and the separation surface of the two solutions must be pulled to the core. Plan 1: The interior channel is arranged on the interior wall of the molded part. In order to reduce the influence of molten metal on the core during the rapid pressing phase of the channel, the outer channel of the casting is arranged away from the channel. kernel cursor; In order to compensate for the removal of filling pressure, the inner and outer channels of the casting are connected in a non-horizontal linear manner, and only one corner is set to connect. In the second plane, the ingate is placed obliquely on the upper plane of the casting. In order to reduce the impact of the entire filling process on the core, the length of the horizontal channel is extended. The thickness of the runner can be calculated by the following formula.

D=(5~8)T(2)

In the formula: D is the thickness of the side slide, mm; T is the thickness of the inner slide, mm. Taking D = 8 mm, in order to facilitate unmolding of the molded part, adjust the clearance angle of the side slide to 10°.

2.2.3 Core design

The sprue is the channel through which the molten metal enters the mold cavity from the pressure chamber, and its size corresponds to the diameter of the pressure chamber. The castings targeted by this design are small parts, but they are free from machining. In order to ensure that the gas slag can be effectively discharged from the mold cavity, the total volume of the overflow tank is designed to be greater than or equal to 1.2. times the volume of the cast; this casting requires several base draws for the institution. To ensure that the casting can come out smoothly, the volume of each core draw slider should be greater than or equal to 1/3 of the casting volume considering the layout of each mold structure, the die casting machine final selected; was the DCC280 horizontal cold chamber die casting machine, and the diameter of the pressure chamber was chosen to be 50mm, and the remaining thickness of the material is set to 16mm.

2.2.4 Overflow tank design

Design principles of overflow tank: ① The last part filled with molten metal is at the right end of the casting in plane 1, and at both ends of the lower bottom of the casting in plane 2 , therefore an overflow tank is placed at the end of the different planes; ② The place where the molten metal first hits and the wall thickness of the casting, so An overflow groove is set up corresponding to the upper and lower sides of the runner. In plane 1, the wall thickness of the arc branch runner corresponding to the upper and lower sides is too thin, so no overflow groove is provided; currents are easily generated at the confluence of molten metal, so in plane 1 the arc branch runner is An overflow tank is provided above and below the apex.


3Numerical simulation analysis

Save the 3D model of the die casting part with the casting system in stl format and import it into CAE software for meshing. Due to the complex structure of the casting, its minimum wall thickness is different from the minimum wall thickness of the casting system. , a non-uniform mesh is therefore used. Divide the grate size of the pouring and drainage system into 0.8mm and divide the pouring grate size into 10mm to generate a total number of grates. The casting material is YL113 aluminum alloy and the mold material is H13 steel. The casting process parameters are shown in Table 2.

1726822656354307.png

Table 2 Casting process parameters

3.1 Analysis of the filling process

The filling process for option 1 is shown in Figure 4. The molten metal first enters the core. After passing through the arc branching channel at t = 0.160 5 s, it is sprayed down the rib plate and returns to the arc wall along the rib wall at t = 0.162 0 s. , the molten metal passes through the main core channel and the left branch core, pulverized to the bottom of the intersection of the ribs and disperses the filling along the ribs at t=0.168 2; At s, after the filling at the top of the arc is completed, the left side molten metal is filled in the direction of the casting sleeve along the upper and lower planes and ribs at t = 0.176 0 s, the filling of ; the molten metal is complete and the mold cavity is almost completely filled, without any filler gaps. From the perspective of the whole filling process, the flow of molten metal is basically smooth, with a certain degree of splashing, but the splashing area is the area of ​​the ribs and the appearance of the workpiece casting is not affected by the main channel and the left; The branch paths are filled with molten metal in the left branch. The inner wall on the right side of the channel converges and filling occurs. Slag inclusion cannot be effectively removed by the overflow tank; the molten metal converges toward the inner wall of the sleeve connection area, and defects such as air entrainment, cold sealing, shrinkage cavities and shrinkage porosity may occur; the overflow tank is unreasonable. There is no overflow groove provided in the upper and lower sleeve areas.

1726822672802685.png

Figure 4 Simulation results of the filling process of Scheme 1

The filling process of option 2 is shown in Figure 5. The molten metal enters the side channel from the core. At t = 0.451 2 s, it enters the casting cavity through the main channel, after hitting the arc wall, the liquid flows up and down along the arc wall at t = 0.531 8; s, the metal The liquid enters the casting cavity through the two connection sprues. At the main core, molten metal flows slowly to the left side of the core due to core obstruction, as shown in Figure 5, which can lead to casting. generation of eddy currents and air entrainment. At t=0.550 5 s, the filling of the arc surface of the casting is completed, and the molten metal fills the ends of both sides of the casting. At t = 0.551 8 s, the molten metal is completely filled and the mold cavity is completely filled without any filling voids. From the perspective of the whole filling process, plane 2 first fills the sleeve connection area due to the obstruction of the core, and there is a certain degree of splashing during the filling process . The area affected by splashing is the appearance surface of the casting; the flow of molten metal is affected by the curved ribbed plate, and there is air entrainment in certain areas and eddy currents; the molten metal converges to the outer surface of the casting, and an overflow groove cannot be installed in the corresponding area.

1726822688380233.png

Figure 5 Simulation results of the second schematic filling process

There is a certain degree of splashing during the filling process of both pouring methods, but the splashing area in the first option is the side wall of the rib, while the splashing area in the second option is the arc surface of the casting, which may cause burrs on the arc surface of the casting. From the point of view of technical requirements and the absence of the need for processing, the first option is more reasonable.

3.2 Analysis of the solidification process

The solidification process in Scheme 1 is shown in Figure 6. The molten metal first begins to solidify at the edge of the casting, then solidifies from the edge toward the sprue. When t = 1.528 3 s, the ingate begins to solidify, and the main body of the casting is basically solidified, but some wall thickness areas are not yet completely solidified. From the perspective of the entire solidification process, some areas are not solidified in sequence during solidification. The rib walls and the inner walls of the sleeve connection area are solidified first, while the upper and lower planes are the wall thickness areas and are solidified later. Therefore, shrinkage porosity and shrinkage holes are easily formed in this area. The solidification process of Scheme 2 is shown in Figure 7. Compared with Scheme 1, the solidification time of ingate is longer, but the problem of the sleeve connection area is consistent with Scheme 1, and At the cross connection between the rib plate and the inner wall, the rib wall and the inner wall solidify first and there is no ingate to match it. As a result, isolated liquid phase zones will appear in these areas, leading to shrinkage and shrinkage cavities in the castings in these areas.

1726822715313358.png

Figure 6 Simulation results of the solidification process of Scheme 1

1726822725923853.png

Figure 7 Simulation results of the solidification process of Scheme 2

3.3 Defect analysis

Figure 8 shows the shrinkage and shrinkage hole distribution diagrams of the two solutions. Casting defects are concentrated in wall thickness areas such as the sleeve connection platform area, some rib plate intersection areas, and the upper and lower surfaces of the through plate area. This is mainly because the wall thickness in these areas is thicker than in others. During solidification, the temperature of these areas is higher than that of the surrounding thinner walls. Therefore, the molten metal slowly solidifies, creating a gap with the surrounding thin-walled areas, and cannot be replenished by the molten metal when it is. completely solidified, resulting in defects such as shrinkage and shrinkage cavities. Comparing the two planes, the defect locations are approximately the same, but the second plane does not set a corresponding entry at the rib intersection, so there are more defects in the rib intersection area than the first. After removing the overflow tank, the volume of shrinkage porosity and shrinkage porosity in Scheme 1 is 0.056 cm³, while the volume of shrinkage porosity and shrinkage pores in Scheme 2 is 0.083 cm³. Therefore, Scheme 1 is better in terms of reducing shrinkage and porosity. shrinkage porosity.

Image WeChat_20240920165424.png

Figure 8 Distribution diagram of shrinkage porosity and shrinkage cavities

Comprehensive comparison of the two process options, the second option is simpler in terms of removing the remaining material, but in terms of removal and removal holes, the first option produces fewer defects, the second option is more cumbersome when the opening of the mold, with the exception of; the upper and lower parts along the separation surface. In addition to opening the mold, the mold needs to be opened in the tangential direction of the branch core, which complicates the production process. Therefore, Plan 1 was selected as the subsequent process improvement plan.


4. Process improvement

4.1 Optimization plan

In addition to the problems with filling the initial process, the cross section of the main channel in the original plane was too large, making it difficult to remove the subsequent machining allowance from the casting, so adjustments were made. brought to casting. and drainage system. In order to solve the problem that the sleeve connection plane is too thick and the distance between the inner sprues is too large to achieve effective power supply, a cooling system has been added to optimize it.

During the filling process, channel corners are added to reduce turbulence generated when liquid flows from the core into the channel and further compensate for the filling pressure. The main channel is canceled and one channel is added to the left and right; instead. Plug the sprue so that the metal liquid from both sides of the sprue can converge into the overflow groove at the top of the arc. Arrange an overflow groove in the tangential connection platform area of ​​the sleeve to facilitate the removal of slag inclusions and gases before the metal liquid converges to the sleeve wall, reduce the intensity of impact of the liquid flow at the confluence and avoid insulation by the cold at the level of the sleeve wall. At the same time, an exhaust slot is put in place and the corresponding upper and lower overflow slots are connected with the exhaust slot to facilitate the removal of gases and eliminate the existence of pores inside of the molded part. The optimization of the pouring and drainage system is shown in Figure 9.

Image WeChat_20240920165427.png

Figure 9 Improved pouring and drainage system design

During the solidification process, in order to solve the problem of isolated liquid phase areas in the wall thickness of the upper and lower surfaces of the connection area of ​​the sleeve and the through plate, a water pipe with a temperature of 20° was placed above. to optimize the solidification sequence of the casting. In addition, the added door can effectively delay the solidification of the inner wall, ensure that the complete solidification of the inner wall lags behind the wall thickness area, and can also reduce the wall thickness area. The layout of the cooling water path is shown in Figure 10, and the cooling process parameters are shown in Table 3.

Image WeChat_20240920165430.png

Figure 10 Cooling water path distribution diagram

Image WeChat_20240920165432.png

Table 3 Cooling process parameters

4.2 Simulation of the optimization plan

The optimized plan is simulated, and the filling and solidification process is shown in Figure 11. It can be seen that the whole filling process is smooth. The molten metal enters the cavity from the central opening and fills smoothly along the ribs, and converges to the upper overflow groove, which avoids cold insulation caused by the confluence of the molten metal on the wall interior. At the same time, the overflow groove provided in the tangential direction of the sleeve also plays a role in guiding the flow. During the solidification process, the surface of the added cooling system solidifies in advance compared to the thin-walled area, allowing the casting to solidify in an orderly manner.

1726822868917143.png

Figure 11 Changes to the filling process and solidification temperature field after optimization

Figure 12 shows the distribution of shrinkage porosity and shrinkage holes in the casting part after optimization. It can be seen that the surface defects in the connection area of ​​the sleeve have been effectively resolved, and there is no cold insulation phenomenon on the inner wall of the casting.

Image WeChat_20240920165437.png

Figure 12 Distribution diagram of shrinkage and shrinkage holes

4.3 Verification of the optimization plan

In order to verify the feasibility of the optimized scheme, the die casting process parameters in Table 4 were used to make test prototypes of the optimized scheme.

1726822890772298.png

Table 4 Die Casting Trial Production Process Parameters

Based on the calculation of the clamping force, the DCC280 Lijin die casting machine with a clamping force of 2,800 kN was selected for the production of trial molds. The basic information parameters of the die casting machine are shown in Table 5. The actual production hinge bracket is shown. in Figure 13. There are no burrs on the appearance surface. The X-ray inspection is shown in Figure 14. No shrinkage porosity, shrinkage cavities or cold insulation defects were found. It meets technical requirements and can be mass produced.

1726822903976655.png

Table 5 Parameters of Lijin DCC280 Die Casting Machine

Image WeChat_20240920165446.png

Figure 13 Actual image of hinge bracket casting

1726822922459365.png

Figure 14 X-ray defect detection chart

5Conclusion

(1) According to the hinge bracket structure and technical requirements, two die casting processes are designed. Through CAE software, the mold filling and solidification process is simulated and analyzed, and a solution for further optimization is selected by comparison.

(2) By improving the pouring and drainage system and adding cooling water channels, the shrinkage defects, shrinkage holes and cold insulation in the castings of the hinge brackets have been solved , meeting the technical requirements and providing an efficient process production model for the production of such parts. .

Die Casting Machine Inquiry: 15910974236

Daguang focuses on providing solutions such as precision CNC machining services (3-axis, 4-axis, 5-axis machining), CNC milling, 3D printing and rapid prototyping services.

CNC Experts

Picture of JinShui Chen

JinShui Chen

Rapid Prototyping & Rapid Manufacturing Expert

Specialize in CNC machining, 3D printing, urethane casting, rapid tooling, injection molding, metal casting, sheet metal and extrusion

CNC Recent Posts

CNC News

Welcome to GreatLight Metal,Maximum Processing Size 4,000 mm

Precision Machining CNC Quote Online

Loading file

Upload Click here to upload or drag and drop your model to the canvas.

The model is too large and has been resized to fit in the printer's build tray. [Hide]

The model is too large to fit in the printer's build tray. [Hide]

The model is too large, a fitting printer is selected. [Hide]

The model is too small and has been upscaled. [Hide]

Warning: The selected printer can not print in full color [Hide]

Warning: obj models with multiple meshes are not yet supported [Hide]

Warning: Unsupported DXF entity  [Hide]

Warning: could not arrange models [Hide]


File Unit:      
Scale:
%
L × W × H:
X: × Y: × Z:  cm 
Rotation:
X: ° Y: °  
⚡ Instant Quote for Precision Manufacturing

Submit your design files (STEP/IGES/DWG) and receive a competitive quote within 1 hour, backed by ISO 9001-certified quality assurance.

📋 How It Works

  1. Upload & SpecifyShare your 3D model and select materials (Aluminum/Stainless Steel/Titanium/PEEK), tolerances (±0.002mm), and surface treatments.

  2. AI-Powered AnalysisOur system calculates optimal machining strategy and cost based on 10+ years of automotive/aerospace data.

  3. Review & ConfirmGet a detailed breakdown including:
    - Volume pricing tiers (1-10,000+ units)
    - Lead time (3-7 days standard)
    - DFM feedback for cost optimization

Unit Price: 

Loading price
5 Axis CNC Machining Equipment
4 Axis CNC Machining Equipment
3 Axis CNC Machining Equipment
CNC Milling & Turning Equipment
Prototype and Short-Run Injection Moldings Exact plastic material as final design
Volume Metal Die Casting Services - Precision Cast Parts
Bridge the Gap From Prototype to Production – Global delivery in 10 days or less
Custom high-precision sheet metal prototypes and parts, as fast as 5 days.
Custom Online 3D Printing Services
Custom Online 3D Printing Services
Custom Online 3D Printing Services
Design Best Processing Method According To 3D Drawings
Alloys Aluminum 6061, 6061-T6 Aluminum 2024 Aluminum 5052 Aluminum 5083 Aluminum 6063 Aluminum 6082 Aluminum 7075, 7075-T6 Aluminum ADC12 (A380)
Alloys Brass C27400 Brass C28000 Brass C36000
Alloys Stainless Steel SUS201 Stainless Steel SUS303 Stainless Steel SUS 304 Stainless Steel SUS316 Stainless Steel SUS316L Stainless Steel SUS420 Stainless Steel SUS430 Stainless Steel SUS431 Stainless Steel SUS440C Stainless Steel SUS630/17-4PH Stainless Steel AISI 304
Inconel718
Carbon Fiber
Tool Steel
Mold Steel
Alloys Titanium Alloy TA1 Titanium Alloy TA2 Titanium Alloy TC4/Ti-6Al 4V
Alloys Steel 1018, 1020, 1025, 1045, 1215, 4130, 4140, 4340, 5140, A36 Die steel Alloy steel Chisel tool steel Spring steel High speed steel Cold rolled steel Bearing steel SPCC
Alloys Copper C101(T2) Copper C103(T1) Copper C103(TU2) Copper C110(TU0) Beryllium Copper
Alloys Magnesium Alloy AZ31B Magnesium Alloy AZ91D
Low Carbon Steel
Alloys Magnesium Alloy AZ31B Magnesium Alloy AZ91D
ABS Beige(Natural) ABS Black ABS Black Antistatic ABS Milky White ABS+PC Black ABS+PC White
PC Black PC Transparent PC White PC Yellowish White PC+GF30 Black
PMMA Black PMMA Transparent PMMA White
PA(Nylon) Blue PA6 (Nylon)+GF15 Black PA6 (Nylon)+GF30 Black PA66 (Nylon) Beige(Natural) PA66 (Nylon) Black
PE Black PE White
PEEK Beige(Natural) PEEK Black
PP Black PP White PP+GF30 Black
HDPE Black HDPE White
HIPS Board White
LDPE White
This is a finish of applying powdered paint to the components and then baking it in an oven, which results in a stronger, more wear- and corrosion-resistant layer that is more durable than traditional painting methods.
No coating required, product’s natural color!
This is a finish of applying powdered paint to the components and then baking it in an oven, which results in a stronger, more wear- and corrosion-resistant layer that is more durable than traditional painting methods.
This finishing option with the shortest turnaround time. Parts have visible tool marks and potentially sharp edges and burrs, which can be removed upon request.
Sand blasting uses pressurized sand or other media to clean and texture the surface, creating a uniform, matte finish.
Polishing is the process of creating a smooth and shiny surface by rubbing it or by applying a chemical treatmen
A brushed finish creates a unidirectional satin texture, reducing the visibility of marks and scratches on the surface.
Anodizing increases corrosion resistance and wear properties, while allowing for color dyeing, ideal for aluminum parts.
Black oxide is a conversion coating that is used on steels to improve corrosion resistance and minimize light reflection.
Electroplating bonds a thin metal layer onto parts, improving wear resistance, corrosion resistance, and surface conductivity.
This is a finish of applying powdered paint to the components and then baking it in an oven, which results in a stronger, more wear- and corrosion-resistant layer that is more durable than traditional painting methods.
This is a finish of applying powdered paint to the components and then baking it in an oven, which results in a stronger, more wear- and corrosion-resistant layer that is more durable than traditional painting methods.
Please provide additional text description for other surface treatment requirements!
Material
Material
  • CNC Metals
    • Aluminum
    • Brass
    • Stainless steel
    • Inconel718
    • Carbon Fiber
    • Tool Steel
    • Mold Steel
    • Titanium
    • Alloy Steel
    • Copper
    • Bronze
    • Low Carbon Steel
    • Magnesium
  • CNC Plastics
    • ABS
    • PC
    • PMMA (Acrylic)
    • PA (Nylon)
    • PE
    • PEEK
    • PP
    • HDPE
    • HIPS
    • LDPE
Printer
Printer
  • CNC Metals
    • 5 Axis CNC Machining
    • 4 Axis CNC Machining
    • 3 Axis CNC Machining
    • CNC Milling & Turning
    • Rapid Tooling
    • Metal Die Casting
    • Vacuum Casting
    • Sheet Metal Fabrication
    • SLA 3D Printing
    • SLS 3D Printing
    • SLM 3D Printing
  • Rapid Prototyping
    • Design Best Processing Method According To 3D Drawings
Post-processing
Post-processing
  • As Machined(Product’s natural color)
  • Sand Blasting
  • Polishing
  • Brushed Finish
  • Anodizing
  • Black Oxide
  • Electroplating
  • Paint Coating
  • Powder Coating
  • Other surface treatment requirements
Finalize
The world's first CNC machining center that dares to provide free samples!

Free for first product valued at less than $200. (Background check required)

precision machining cnc quote online

15 Years CNC Machining Services

When you’re ready to start your next project, simply upload your 3D CAD design files, and our engineers will get back to you with a quote as soon as possible.
Scroll to Top

ISO 9001 Certificate

ISO 9001 is defined as the internationally recognized standard for Quality Management Systems (QMS). It is by far the most mature quality framework in the world. More than 1 million certificates were issued to organizations in 178 countries. ISO 9001 sets standards not only for the quality management system, but also for the overall management system. It helps organizations achieve success by improving customer satisfaction, employee motivation, and continuous improvement. * The ISO certificate is issued in the name of FS.com LIMITED and applied to all the products sold on FS website.

greatlight metal iso 9001 certification successfully renewed
GB T 19001-2016 IS09001-2015
✅ iso 9001:2015
greatlight metal iso 9001 certification successfully renewed zh

IATF 16949 certificate

IATF 16949 is an internationally recognized Quality Management System (QMS) standard specifically for the automotive industry and engine hardware parts production quality management system certification. It is based on ISO 9001 and adds specific requirements related to the production and service of automotive and engine hardware parts. Its goal is to improve quality, streamline processes, and reduce variation and waste in the automotive and engine hardware parts supply chain.

automotive industry quality management system certification 01
Certification of Production Quality Management System for Engine Hardware Parts Engine Hardware Associated Parts
automotive industry quality management system certification 00
发动机五金零配件的生产质量管理体系认证

ISO 27001 certificate

ISO/IEC 27001 is an international standard for managing and processing information security. This standard is jointly developed by the International Organization for Standardization (ISO) and the International Electrotechnical Commission (IEC). It sets out requirements for establishing, implementing, maintaining, and continually improving an information security management system (ISMS). Ensuring the confidentiality, integrity, and availability of organizational information assets, obtaining an ISO 27001 certificate means that the enterprise has passed the audit conducted by a certification body, proving that its information security management system has met the requirements of the international standard.

greatlight metal technology co., ltd has obtained multiple certifications (1)
greatlight metal technology co., ltd has obtained multiple certifications (2)

ISO 13485 certificate

ISO 13485 is an internationally recognized standard for Quality Management Systems (QMS) specifically tailored for the medical device industry. It outlines the requirements for organizations involved in the design, development, production, installation, and servicing of medical devices, ensuring they consistently meet regulatory requirements and customer needs. Essentially, it's a framework for medical device companies to build and maintain robust QMS processes, ultimately enhancing patient safety and device quality.

greatlight metal technology co., ltd has obtained multiple certifications (3)
greatlight metal technology co., ltd has obtained multiple certifications (4)

Get The Best Price

Send drawings and detailed requirements via Email:[email protected]
Or Fill Out The Contact Form Below:

All uploads are secure and confidential.