First Article Inspection Process Steps for Machined Parts
A working sequence for engineers and buyers who need the first production-representative part verified before the lot runs. It covers drawing review, ballooning, setup checks, measurement method choice, and the report that closes the FAI.

In this article
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
What matters most
What an FAI covers and when it is required
A first article inspection proves that the first production-representative part matches the drawing, the purchase order, and any referenced specification. It is not a sample check. It is a full record of every characteristic, measured and traceable, signed by the people who made and checked the part.
Run one at new part introduction. Run it again after a design change, a process change, a tooling or program change, or a production gap, commonly 12 months or more without running the part. Automotive work under IATF 16949 and medical work under ISO 13485 usually add their own triggers on top of that baseline.
The output is a report that a customer, an auditor, or a second engineer can read without calling you. If the report needs a phone call to interpret, it is not finished.
- 1New partFirst run at any supplier, or first run after a source change.
- 2ChangeDrawing revision, material, finish, machine, fixture, or CAM program.
- 3Gap12 months or more with the part out of production.
Drawing review and ballooning
Read the drawing at the revision called out on the purchase order. Confirm that revision matches the 3D model and every referenced specification. A mismatched revision is the most expensive error in the process because it invalidates every measurement that follows, and it is found late.
Check the title block for general tolerances. Untoleranced dimensions commonly fall in the ±0.1 mm to ±0.5 mm band depending on the standard invoked, and that band decides which features can be checked with a caliper and which need a CMM. Note any GD&T datum reference frame, any surface finish callout, and any note that changes inspection scope.
Ballooning turns the drawing into an auditable list. Give every dimension, note, specification, and GD&T callout a unique number. A moderately complex machined bracket carries 80 to 250 characteristics. A simple shaft might carry 30. Balloon in a fixed order, left to right and top to bottom, so a second inspector can follow the same path.
Keep the ballooned drawing and the characteristic list linked by the same numbers. When a characteristic fails, the number is how you find it, fix it, and re-measure it without re-reading the whole drawing.
- 1Revision checkPO revision, model revision, and specification revision must agree.
- 2Characteristic count80–250 on a typical bracket; 30 on a simple shaft.
- 3Numbering orderFixed path, so a second inspector repeats it exactly.
Setup verification and first-part measurement
Before the first part is inspected, confirm that the setup matches what the FAI assumes. Check the CNC program revision, the fixture and workholding, the tool list with correct geometry, and the machine the part will actually run on. Confirm probe calibration and tool presetter offsets are current.
For tight-tolerance features, take a warm-up cut or run a test part on scrap material. A machine that has been idle overnight is not at thermal equilibrium, and a ±0.005 mm feature will show it. Let the part and the gage settle to the same temperature before measuring.
Measurement combines CMM, hand gaging, and surface and material checks. A bridge CMM suits true position, profile of a surface, and any characteristic that depends on a datum reference frame. Hand tools such as micrometers, bore gages, height gages, and pin gages are faster and often more direct for simple sizes.
Method choice has real trade-offs. A CMM is the wrong call for a 0.01 mm bore diameter on a deep hole, where a plug gage or bore gage reads more directly. Surface finish goes to a profilometer against the specified Ra, commonly Ra 0.8–1.6 μm on machined surfaces, and every reading is recorded with the instrument that produced it.
- 1Program and fixtureConfirm revision, workholding, and tool geometry before the first cut.
- 2Thermal stateWarm-up cut or scrap test part on tight features.
- 3Gage choiceCMM for datum-dependent callouts; hand tools for simple sizes.
Certificates, documentation, and nonconformances
The FAI also covers material, finish, and special processes. Collect mill certificates with heat number and chemistry. Confirm the grade and condition against the drawing. Verify heat treat, anodize, passivation, or plating certificates including coating thickness and any specified test results.
For critical features, confirm that the process specification revision on the certificate matches the drawing. A certificate at the wrong revision is a finding, even when the part measures good.
Documenting results means recording the nominal, the tolerance, the actual measured value, and the gage used, for every characteristic. Report values to the resolution the gage supports. Quoting 0.0001 mm from a hand micrometer overstates confidence. Note ambient temperature where the drawing calls for it, since 20 °C is the reference and a warmer shop biases measurements on aluminum.
When a characteristic fails, stop and write it up. Record the measured value, the requirement, and the likely cause. Then choose rework, deviation, or scrap. A deviation needs customer approval before the lot runs. After rework, re-inspect the affected characteristics and attach the new readings to the same report.
- 1Mill certHeat number, chemistry, grade, and condition.
- 2Finish certCoating thickness and test results at the drawing revision.
- 3Value and gageNominal, tolerance, actual, and instrument for every line.
- 4NonconformanceRework, deviation, or scrap, then re-inspect.
Approval, sign-off, and revision control
Sign-off closes the FAI. The inspector signs the measurements, the quality engineer signs the report, and the customer approves where the purchase order requires it. Each signature carries a date and a revision reference.
Store the report with the ballooned drawing, the characteristic list, the certificates, and any deviation approvals. When the drawing revision changes, the FAI does not carry over. Open a new one, even if the change looks small, because the characteristic list changes with it.
The most common failure points are a stale revision, a missing gage record, and a nonconformance that was fixed on the floor but never written up. Each one is cheap to prevent at step one and expensive to explain at an audit.
- 1SignaturesInspector, quality engineer, and customer where required.
- 2Revision changeNew FAI, new characteristic list, no carry-over.
- 3Audit trailReport, ballooned drawing, certificates, and approvals in one file.
First article inspection process steps in order
- 1Review the drawing and specificationMatch the PO revision to the model and referenced specs. Read general tolerances and GD&T datums. Stop if any revision disagrees.
- 2Balloon the drawingNumber every dimension, note, and callout in a fixed path. Build the characteristic list from those numbers. Expect 80–250 lines on a bracket.
- 3Verify setup before cuttingConfirm program revision, fixture, tool list, and machine. Check probe calibration and tool presetter offsets. Warm up on tight features.
- 4Measure the first partUse CMM for position and profile, hand gages for simple sizes, and a profilometer for Ra. Record nominal, tolerance, actual, and gage for every line.
- 5Collect material and process certificatesPull mill certs with heat number, plus heat treat, anodize, passivation, or plating certs at the drawing revision.
- 6Handle nonconformancesWrite up the failure, choose rework, deviation, or scrap, get customer approval for deviation, then re-inspect the affected characteristics.
- 7Sign off and control the revisionInspector and quality engineer sign with date and revision. File the report with the ballooned drawing and certificates. Re-open on any revision change.
Which measurement method for which characteristic
| Characteristic | Method | Why |
|---|---|---|
| True position | CMM | Needs a datum reference frame |
| Profile of a surface | CMM | Dense point data across the surface |
| Simple outside diameter | Micrometer | Faster, direct read |
| Deep small bore | Plug or bore gage | Reads the hole, not the access |
| Bolt circle hole location | CMM | Position depends on datums |
| Surface finish Ra | Profilometer | Only instrument that reports Ra directly |
| Hardness after heat treat | Hardness tester | Process certificate plus part check |
| Thread callout | Thread gage | Go/no-go matches the spec |
The step that decides the rest
Get the drawing revision and the ballooned characteristic list right, and the remaining steps are execution. Get them wrong, and every measurement after that is wasted work.
Common questions
How long does a first article inspection take?
It depends on the characteristic count. A simple shaft with 30 characteristics is a few hours of measurement. A bracket with 200 characteristics plus certificates and a CMM program is typically one to two days.
The long pole is usually the CMM program and the certificate collection, not the measuring itself.
Can the FAI be done on a part from the production lot?
Yes, as long as the part is production-representative: same machine, same program, same fixture, same material lot as the rest of the run.
A part made on a different machine or with a temporary setup is not a valid first article.
What happens if one characteristic fails?
The FAI is not closed. The failure is written up with measured value and requirement, then routed to rework, deviation, or scrap.
After rework, re-inspect the affected characteristics and attach the new readings. A deviation needs customer approval before the lot runs.
Does a drawing revision always trigger a new FAI?
Treat it as a new FAI. Even a small revision changes the characteristic list, and a report built on the old list cannot be audited against the new drawing.
If the customer formally waives the new FAI, keep that waiver in the file.
What accuracy should the CMM have for an FAI?
A bridge CMM stating roughly 2–3 µm plus 3–5 µm/m is appropriate for position and profile tolerances of 0.1 mm and tighter.
Below that, fixturing and temperature dominate the error, so control the room before buying a better machine.
Is a first article inspection the same as a PPAP?
No. The FAI is one element inside a PPAP submission. PPAP adds process capability studies, control plans, and other documents on top of the FAI report.
Automotive programs often need both, and the FAI feeds the PPAP package.